Camrova resources_ boleo project and corporate update – junior mining network

VANCOUVER, BC–(Marketwired – January 13, 2017) – Camrova Resources Inc. Data recovery macbook ( formerly Baja Mining Corp.), (the “Company”) (TSX VENTURE: CAV) (OTCQB: BAJFF) is pleased to report that Tom Ogryzlo (Interim CEO) and Nigel Kirkwood (CFO), recently attended a meeting of the Board of Directors of Minera y Metalúrgica del Boleo, S.A. Data recovery los angeles P.I. Database yml de C.V. Database in excel (“MMB”) at site where they were presented with an update on operations for 2016, the MMB Business Plan and Budget for 2017 and an updated LOM Plan containing projections through to 2031, when mining operations are forecast to terminate.

Camrova management also went underground to observe the recent progress that has been made through application of the newly introduced mining methods. G info database The Company is now able to provide an update on developments relating to the mining activities and process plant.

During 2016 MMB management, employees and contractors continued to work diligently to make advances to achieve normalized operations and become profitable. Database book MMB management reported that operations during 2016 are currently forecast as follows:

• Copper cathode production of 14,284 tonnes, which is double that of the prior year, but lower than the target of 22,574 tonnes due to unanticipated plant downtime related to unscheduled maintenance, union action, Hurricane Newton and lower grade plant feed material and recovery rates than predicted; the target for 2017 calls for total production in excess of double that achieved in 2016

• Average copper recovery of 75% with a high of 81% in the month of May. Q prime database A number of plant modifications were completed during the year to improve plant performance;

• Completion of the commissioning of the cobalt and zinc sulphate circuits and achievement of commercial production of 419 tonnes and 1,444 tonnes, respectively;

• Mining production of 1.4 million tonnes, which is lower than targeted due to the continued testing of underground methods. Top 10 data recovery tools Surface mining production was increased to partly offset the lower underground mining production;

• Initiated trial mining in October 2016 using semi-shield equipment for roof support to carry out underground shortwall mining.


Data recovery laptop Mobile Roof Support (MRS) retreat mining with modified support methods was resumed providing improved safety and roof stability for advance areas. Data recovery flash drive New customized equipment was acquired and commissioned for trial application for each mining method, including smaller sized equipment, road headers, a rock grinder and side dump loader.

MMB management presented a Business Plan and Budget for 2017 to the Board of Directors (the “2017 Budget”). Data recovery cost The MMB Board gave tentative approval, subject to obtaining the subsequent approval by the KORES Board. Data recovery galaxy s5 The key operational objectives at Boleo for 2017 are to achieve stable ore production, to enhance both plant availability and recovery, and to attain normalized plant operation.

The Mine Plan targets ore production for 2017 of 2.7 million tonnes, with surface mining contributing 2.0 million tonnes and underground contributing 0.7 million tonnes. Database key field The underground target is expected to be accomplished by using customized semi-shield mining and MRS retreat mining, employing mechanized mining methods to maximize underground production. Data recovery nashville Efforts will continue to recruit additional skilled underground mining personnel with a targeted maximum workforce of 300 persons during Q4 2017. Data recovery minneapolis Tunnel advances in the three underground mines currently in operation and in three new underground mines are targeted to open up over 18,000 metres of haulageways and panels in difficult ground conditions. Database 4 net Surface production in 2017 will include the development of the Purgatorio area targeting higher grade ore production, which will require significant waste removal. Iphone 6 data recovery software free Surface operations will work to minimize ore loss and dilution through grade control and selective mining targeting an average copper grade of 1.16%. Database usa reviews Surface operations strip ratio is expected to exceed be about 8:1.

Plant operations for 2017 are targeting to produce 30,000 tonnes of cathode copper with monthly production exceeding 2,500 tonnes per month following the annual plant shut-down in January 2017 for planned maintenance and processing upgrades. Easeus data recovery 94fbr Plant throughput is targeted at 2.8 million tonnes at an average feed grade of 1.24% copper, and a targeted recovery exceeding 84%. Database join Initiatives are planned to reduce plant operating and maintenance costs in 2017. H2 database download Monthly production of cobalt and zinc sulphate is targeted to exceed 50 tonnes and 770 tonnes, respectively.

Budgeted capex of US$45 million is mainly comprised of expenditures on new equipment for underground and surface mining and planned expansion of the tailings storage facility.

The 2017 Budget projects a cash shortfall of approximately US$160 million before funding. H2 database url Funding of US$30 million of the shortfall has previously been approved by KORES, however the 2017 Budget and required balance of funding of US$130 million, remains subject to the approval of the MMB Board pending receipt of KORES in January 2017.

It is unclear at this time to what extent this cash short fall will be covered by new equity and/or new shareholder or third-party loans. Data recovery boot disk This may well result in a further decrease in Camrova’s ownership of MMB, in addition to that which may arise in respect of the US$346 million of cash call funding already extended to MMB as at December 31, 2016. 990 database The extent of any dilution to Baja’s current 10% shareholding in MMB is pending finalization of the Shareholders Agreement (see below) and the ultimate form of the cash call participation (ie. Data recovery hard drive cost shareholder loan or equity).

MMB management presented an updated LOM Plan that was prepared at the end of 2016. Data recovery knoxville The LOM Plan has a 15 year horizon ending in 2031, during which average annual mine production is projected to be 3.1 million tonnes (underground – 1.9 million tonnes; surface mining – 1.2 million tonnes), equivalent to a total production of 45.9 million tonnes, with projected average grades of 1.3% copper, 0.07% cobalt and 0.5% zinc. 7 data recovery keygen LOM average mining cost is projected at US$14.30 per tonne. H2 database client During the LOM, plant production is projected at approximately 528,000 tonnes of cathode copper, 20,000 tonnes of cobalt and 270,000 tonnes of zinc sulphate, maximizing metal production by increasing processing recoveries. Dayz database Beyond 2031, feasibility studies will be completed to establish a plan to sustain operations as a refinery. I phone data recovery The LOM operations are projected to achieve cash flow breakeven, assuming the refinancing of the MMB senior debt. Database 3d This suggests that distributions or the repayment of loans to Camrova from the Project over the LOM may not be possible.

The Company currently anticipates that the final outstanding issues relating to the new MMB shareholders’ agreement (the “Shareholders’ Agreement”) will be finalized around the middle of January 2017. Yorku database At that time the Company also expects that payment of the first instalment of the Management Services Agreement (the “MSA Margin) owing to the Company by MMB will be made. O o data recovery Further details will be provided when these events occur.

Cinto Colorado continues to wait for a meeting of the Cabildo (elected municipal governing body of the Municipio of Mulegé, the regional municipality) to be held to ratify the Cinto Colorado lease. Data recovery illustrator The Cinto Option Agreement expired on December 31, 2016, as the Company had not undertaken and delivered a NI 43-101 compliant feasibility study for the development of the tailings in accordance with the terms of the Option Agreement, due to the delay in the ratification of the lease. Database management software Cinto Colorado and the Company are in discussions regarding a possible extension of the Option Agreement.

In late December 2016, Mr. Database normalization example Ogryzlo and Mr. Database virtualization Kirkwood met in Vancouver with one of the owners of a small scale copper processing plant in Chile to continue discussions in connection with a possible investment in the operation. Data recovery machine Negotiations are ongoing.

The technical content of this news release has been prepared by Camrova management and approved by Dr. Data recovery cell phone David Dreisinger, Ph.D., P.Eng., F.C.I.M., F.C.A.E, who is a Qualified Person as defined in NI 43-101.